“ProjectProgress has enabled me and my team achieve demonstrable
compliance with the PRINCE2™ project management process which has
satisfied the requirements of both my internal management team and the
OGC Gateway Review panel.”
Appointed as Project Director for the construction of two secure mental
health facilities for the NHS with a combined construction cost of £47m,
Andrew faced the problem of how to demonstrate a sound project
management method and compliance, as a recent OGC Gateway review had
resulted in 13 red lights (immediate action required) and outlined
several key areas to be addressed including risk management..
“Our Stage 1 OGC Gateway Review identified a need to manage risk on our
£12m and £35m projects. We subscribed to ProjectProgress and immediately
moved from red to amber at the next Gateway Review. Working with the
ProjectProgress CRM team we have identified how we can make further use
of the application that will achieve a full Green across the board at
the next review.”
Andrew needed not only assistance with effective risk management, but
the ability to demonstrate compliance with best practice. As an
organisation SLAM NHS is committed to the use of PRINCE2™ on its
projects, and the ProCure21 project was already running under the
auspices of PRINCE2™.
In May 2005 Glenn subscribed to ProjectProgress to obtain assistance in
implementing PRINCE2™ on his projects. Over the next three months 11 of
her 13 red lights were to turn amber.
“We looked at a range of project management software and decided on
Project Progress as we could access the service via the web which meant
didn’t need to interfere with our hospital’s hardware or software, it is
also built completely for the PRINCE2 method. As a government
organisation, we follow PRINCE2™ and this enabled seamless integration
into our project team, both internally and externally.”
Over the last year, my in-house team has double in size which was no
problem for ProjectProgress, I simply invited my additional staff
members to join my project teams via email. ProjectProgress has provided
a standard configuration management system that has allowed all of my
team members get up to speed in the minimum time. In addition the
ProjectProgress CRM division has worked closely with all of my team to
ensure that they understand not only our existing use of the
application, but how I intend fully rolling it out across the
organisation. I now have control of the PRINCE2™ environment in my
organisation which has allowed me to take on an organisation wide
quality assurance role.
Overall summary quote:
What is the meaning of the Red, Amber, Green (RAG) Status in an OGC
Gateway report?
The OGC Supervisory Board has asked all OGC Gateway Review Teams to
agree a RAG status for inclusion in the report at the end of each OGC
Gateway Review. The definitions of the statuses are:
Red - To achieve success the programme or project should take remedial
action immediately. It means 'fix the key problems fast', not 'stop the
project'.
Amber - The programme or project should go forward with actions on
recommendations to be carried out before the next OGC Gateway Review.
Green - the programme or project is on target to succeed but may benefit
from the uptake of the recommendations.